Build progress

Real shipyard photography and muted video — not design renders. Approximately 50% complete; expected delivery March 2027.

From the yard

Build progress

There are 8 build stages to complete. After each build stage, a full survey is conducted by a maritime professional. Reports are available upon viewing. These images and clips document the live build — composite structure, deck assembly, and fit-out underway.

Construction roadmap — 8 stages

50%

  1. Design concept2%
  2. Hulls moulded10%
  3. Hulls joined20%
  4. First deck structure30%
  5. Main deck structure40%
  6. Top deck structure50% · now
  7. Systems & interior fit-out75%
  8. Completion & delivery100%

Shipyard photographs

Interior fit-out in progress — cabinetry layout and curved structure
Internal composite bulkheads and deck assembly in the shipyard
Upper deck mouldings taking shape inside the build hangar
Shipyard team working on fiberglass deck structure

Shipyard video updates

All build videos play silently. Sound has been removed from these clips.