Build progress
Real shipyard photography and muted video — not design renders. Approximately 50% complete; expected delivery March 2027.
From the yard
Build progress
There are 8 build stages to complete. After each build stage, a full survey is conducted by a maritime professional. Reports are available upon viewing. These images and clips document the live build — composite structure, deck assembly, and fit-out underway.
Construction roadmap — 8 stages
50%
- Design concept2%
- Hulls moulded10%
- Hulls joined20%
- First deck structure30%
- Main deck structure40%
- Top deck structure50% · now
- Systems & interior fit-out75%
- Completion & delivery100%